HomeMy Public PortalAbout2016-11-03_Special Council_Public_Agenda PackagePage 1 of 1
MUNICIPAL SPECIAL COUNCIL
AGENDA
Thursday,November 3, 2016 at 8:45 a.m.
Chester Municipal Council Chambers
151 King Street, Chester, NS
1.MEETING CALLED TO ORDER.
2.MINUTES OF PREVIOUS MEETING:
(None at this time)
4.MATTERS ARISING:
4.1 Request for Decision/Direction from Engineering and Public Works Department
regarding Mill Cove Wastewater Treatment Plant Engineering Services RFP
Award.
5.CORRESPONDENCE.
6.NEW BUSINESS.
7.ADJOURNMENT.
REQUEST FOR DECISION/DIRECTION
Prepared By: Matthew S. Davidson, P.Eng Date October 30, 2016
Reviewed By: Tammy S. Wilson, CAO Date October 31, 2016
Authorized By: Tammy S. Wilson, CAO Date October 31, 2016
CURRENT SITUATION
On April 28th, 2016, Municipal Council approved the 2016-17 Capital and Operating Budget. The
Capital Budget included the replacement of the aging Mill Cove Wastewater Treatment Plant
(WWTP). The budget for this project was estimated at $1,455,000, Net HST.
RECOMMENDATION
It is recommended that the Municipality award the Mill Cove Engineering Services, as proposed,
to Hiltz & Seamone, Kentville, Nova Scotia for the amount of $ 84, 918 plus HST.
BACKGROUND
Last fiscal year (FY 2015-2016), Staff with the aid of our previous Engineering Consultant, SNC
Lavalin Inc, worked on the design for the replacement of the aging Mill Cove WWTP. On June 26,
2016, staff made application for Clean Water & Wastewater Funding (CWWF) based on the
design and cost estimate completed last fiscal year. On August 29, 2016, Staff were informed that
the Mill Cove WWTP Replacement Project was an approved project and would receive 75%
funding of the actual eligible costs incurred to a maximum of $1,089,444.
In order to proceed with this project, Staff must procure Engineering Services for the design
review, preparation of specifications and construction management services.
DISCUSSION
Staff issued an RFP, which was sent to the three (3) pre-qualified consultants, of which only two
(2) responded, CBCL Ltd and Hiltz & Seamone. The submissions were deemed to be completed
and evaluated as per the RFP criteria (i.e. Price and Experience).
CBCL Ltd’s proposal provided a thorough understanding of the project, detailed five (5) projects
which of similar scope, as required, and even provided a partial critique of the design to date,
listing a few issues that need to be resolved prior to tendering. The estimated budget proposed
REPORT TO:
Municipal Council
SUBMITTED BY: Engineering & Public Works Department
DATE: October 28, 2016
SUBJECT: Mill Cove WWTP Replacement –
Engineering Services RFP Award
ORIGIN: 2016-2017 Capital Work Program
2 Request For Decision
for the project was $ 99,965 plus HST (lump sum), which includes expenses. The level of effort
proposed a total of 1182 work hours ($84.57/hour).
Hiltz & Seamone’s provided an understanding of the project, however they only generally
mentioned two (2) similar projects, along with other examples of non-specific sewer projects.
Furthermore, the pre-qualification submission did not detail any similar projects. Experience is
an important factor for this project since the Municipality is under a very tight funding deadline,
therefore, specific and demonstrated design and construction familiarity is important. The
estimated budget proposed for the project was $58,938 plus HST, which is not lump sum and
subject to increases relating to additional work effort. The level of effort proposed a total of 736
work hours ($80.07/hour). The evaluation criteria were listed in the RFP, and are summarized
below with the scores, based on the proposal as submitted.
Proponent Price (65%) Experience (35 %) Total
CBCL Limited 19.8 35.0 54.8
Hiltz & Seamone 65.0 17.5 82.5
It is felt that the level of effort is underestimated for both the design review (i.e. 15 days or 120
hours) and construction services (i.e. 14.4 days or 144 hours) in the Hiltz & Seamone submission.
The additional hours at the proposed daily rates for design and inspection would increase the
budget by $9,750 and $16,230, respectively. Therefore, the staff revised project budget is
estimated to be $84, 918 plus HST. It was confirmed with Hiltz & Seamone that they consider the
expenses to be minimal and therefore they are included in the daily rates, however, they have
not committed to the additional work as estimated by staff. The evaluation criteria were listed in
the RFP, and are summarized below with the scores, based on the proposals revised by staff.
Proponent Price (65%) Experience (35 %) Total
CBCL Limited 53.5 35.0 88.5
Hiltz & Seamone 65.0 17.5 82.5
IMPLICATIONS
Policy
Procurement would follow P-04, Procurement Policy as recently amended for Engineering
Services.
3 Request For Decision
Financial/Budgetary
This project is currently funded through the Clean Water & Wastewater Fund (CWWF), receiving
75% ($1,089,444) funding from the Provincial and Federal Governments. The remaining funds
will be sourced from the operating sewer reserves and long term borrowing.
Environmental
N/A
Strategic Plan
2. Continually improve public satisfaction with municipal services;
3. Ensure sufficient infrastructure is available to best serve our residents and businesses;
Work Program Implications
While the current work program did include the replacement of the Mill Cove WWTP, there has
been recent additions to the work program for this fiscal year and possibly next. Therefore, staff
will be preparing a report to update Municipal Council on capital projects and requesting
direction on their reprioritization.
OPTIONS
1. Proceed with award of RFP to the highest rated proposal, as submitted;
2. Proceed with award of RFP to the highest rated proposal, as revised by staff;
3. Defer any decision on the matter and direct staff to bring back further information
as identified by Council.,
ATTACHMENTS
2016-10-03_Project 5 RFP – Mill Cove WWTP
Project 5 –Mill Cove STP Upgrades
Introduction:
The purpose of the Request for Proposals (RFP) is to procure design review, preparation of specifications
and construction management services for the Mill Cove STP Upgrades.This project is funded by CWWF
therefore must be complete in a timely manner to meet funding requirements and complete by March
31, 2018.
Available Information:
Drawings A01, C01 to C06, E01 & E02
Options Analysis letter (March 3, 2016)
Mill Cove STP Survey
Class B Cost Estimate
CWWF funded (award letter/application)
Project Timeline:
RFP due October 19, 2016 at 3pm
Based on award of one (1) pre-qualified firm on October 21, 2016
Design review and specifications completed by November 21, 2016
Tender Period from November 28 –December 23, 2016
Construction Contract Award on January 12, 2017
Construction Substantially completed by August 31, 2017
Project Substantially closed out by March 31, 2018
Service Description:
Design review of STP
Draft Tender Specifications based on Standard Municipal Specifications
Response to Tender queries and issuance of Addenda
Tender submissions review and recommendation
Project kick off meeting with contractor, as well as bi-weekly meetings complete with meeting
minutes
Shop drawing reviews
Design intent queries
Site instruction
Design changes, if required
Liaison with regulatory bodies (i.e. NSE)
Contract administration
Quality assurance program: Preconstruction –review of tender drawings and comment, attend
kick off meeting, inspection of preconstruction site, testing of onsite soil liner materials;
Construction –full time over sight, including testing of materials for compliance; Post
construction –completion of a summarizing report, documenting all aspects of work completed
and inspected, with test results.
Full time inspection based on three (3) months, M-F inspection, 10 hour days
Review as-built files submitted
Preparation of Operation Manual
Project close out with submission of all project documents to MODC
Miscellaneous (i.e. mileage, meals, etc)
MODC may require an insurance premium increase beyond the basic insurance required for the
REI pre-qualification
Proponents are asked to submit a detailed cost estimate (i.e. quantity of hours, unit rates, key personnel
etc.) for each phase of this project (i.e. design, tender, construction and project close out), accompanied
by a list of key personnel roles and responsibilities, any project assumptions and or limitations.
Proponents are encouraged to provide a written summary explaining their cost estimate.
RFP submission evaluation criteria:
65% Cost
35% Experience: Provide five (5) similar wastewater projects that work was completed from
design through to project close out; and provide the project team, the team should have been
involved in the projects listed
The award of work is subject to budget approval.