Audit & Budget Committee
AGENDA
Thursday, January 26, 2017
Chester Municipal Council Chambers
151 King Street, Chester, NS
1. MEETING CALLED TO ORDER.
2. APPROVAL OF AGENDA/ORDER OF BUSINESS.
3. MINUTES OF PREVIOUS MEETING:
3.1. Audit and Budget Committee – August 4, 2016
4. MATTERS ARISING:
4.1. 2017-18 Capital Plan (Power Point and the Spreadsheet Detail in #3)
4.2. Ten Year Capital Plan
4.3. Spread Sheet (Detail)
4.4. Major Projects Summary
4.5. Reserves- Forecast
4.6. Debt Servicing Ratio - Forecast
4.7. Future Schedule for Budget Review (Capital and Operating)
5. NEW BUSINESS.
6. ADJOURNMENT.
Capital Plan
2017-18
Capital
Budget
Summary
Total Capital Budget $8,554,100
Funded By:
Borrowing:$4,593,750 (SW and Sewer)
Operating Reserve:$588,000
Gas Tax Reserve:$197,800
Wind Revenue Reserve:$450,000
Parkland Reserve:$80,000
Sewer Reserve: $233,000
Grants:$2,268,850
Operating Budget:$86,800
Area Rate:$55,900
Recreation
and Parks
2017-18 Capital Projects
Trails:
Surface
Upgrades
$15,000
External Funding:Gas Tax Start: May 2017
Net Costs: 0
Multi-Year Project: Yes
Procurement Method: Heavy Equipment Contract
Description
Trail surface improvements from Chester VIC to
East Chester Recreation Hall.
Rationale
Continuation of surface improvements to meet
Rum Runner Trail standards.
Trails:
Bridge
Evaluation
$25,000
External Funding: Gas Tax Start: June 2017
Net Costs: 0
Multi-Year Project: Yes
Procurement Method: LVP
Description
Conduct an engineered assessment of Little East
River, Goat Lake and Barkhouse Bridges.
Rationale
Ensure trail bridges are structurally safe for all trail
users and to comply with the terms of the LOA
with the Department of Natural Resources.
Trails:
Swing Gates
$7,800
External Funding:Gas Tax Start: June 2017
Net Costs: 0
Multi-Year Project: Yes (complete project in 2018/19)
Procurement Method: LVP
Description
Transition from the current bollard system to a
more user friendly swing gate system at all trail
access points. 10 gates will be installed in
2017/18).
Rationale
Improve access to the trail for emergency and
maintenance vehicles.
Land
Acquisition
$170,000
External Funding: No Start: May 2017
Net Costs: $170,000
Multi-Year Project: TBD
Procurement Method: Alternate Procurement
Description
Acquisition of Parkland-In-Camera Discussion
Rationale
Opportunity to acquire land has arisen
East River
Trail
$25,000
External Funding: TDFEF ($22k)Start: May 2017
Net Costs: $3,000
Multi-Year Project: No
Procurement Method: LVP
Description
Enhance the primitive walking trail on our East
River property and add signage, trail markers and
install a small bridge to connect to the rail trail.
Rationale
Improve opportunity for residents to access this
public property. Full project contingent on grant
funding from TD Friends of the Environment Fund.
Spectacle
Lake Property
Cleanup
$15,000
External Funding:Start: May 2017
Net Costs: $15,000
Multi-Year Project: No
Procurement Method: LVP
Description
Cleanup of municipal property at Spectacle Lake
including the removal derelict cottage and
generator shed.
Rationale
Cottage is in poor condition and is a liability. The
property needs to be cleaned up with all debris
and garbage removed.
Gold River
Park
land/playground
remediation
$10,000
External Funding:Start: May 2017
Net Costs: $10,000
Multi-Year Project: TBD
Procurement Method: LVP
Description
Remediate site after demolition; address
playground equipment deficiencies.
Rationale
With the demolition of the school, site needs to be
tidied up, and deficiencies in playground
equipment addressed (safety)
Admin
2017-18 Capital Projects
PACE BY-LAW
$200,000
External Funding: No Start: August 2017
Net Costs: $200,000
Multi-Year Project: Y
Procurement Method: TBD
Description
Funds for financing either / or energy efficiency
upgrades to properties and well improvements, as
determined by Council. Funds to be repaid by
property owner through taxes
Rationale
Encourages energy efficiency upgrades and
enables property owners to address well
deficiencies
Solid
Waste
2017-18 Capital Projects
Snowplow
Skid Steer
$9,800
External Funding:Valley 86%Start:
Net Costs: $9,800
Multi-Year Project: No
Procurement Method LVP
Description
Snow blower attachment for skid steer
Rationale
This equipment will improve operational readiness
and reduce hand shoveling significantly
Office Roof
$12,000
External Funding:Valley (86%)Start:
Net Costs: $12,000
Multi-Year Project: No
Procurement Method :LVP
Description
Replace roof shingles on roof (replace if required)
Rationale
The office roof has been exposed to significant
wind damage and requires repair.
Main
Leachate
Pump
$20,000
External Funding: Valley 86%Start:
Net Costs: $20,000
Multi-Year Project: No
Procurement Method: LVP
Description
The back up pump is unrepairable and must be
replaced
Rationale
The leachate pump is the main pump in the system
and is difficult to source so a back up is required to
mitigate downtime costs.
Refurbish
sewer truck
$60,000
(Subject to Business
Case-)
External Funding: Valley 86%Start: June 2017
Net Costs: $60,000.00
Multi-Year Project: No
Procurement Method :HVP
Description
Convert sewer truck to a roll of truck
Rationale
Roll off truck will reduce excessive use of loader at
public drop off and be used to move waste from
Sustane for a fee
Second tower
site
$200,000
External Funding:Valley 86%Start: May 2017
Net Costs: $200,000.00
Multi-Year Project: No
Procurement Method :HVP
Description
Build second tower site and 150 meters for original
site. NSDOE approval pending
Rationale
This will let one site rest for extended periods wile
the other is in use
Widening
road to eco-
park
$70,000
External Funding:Valley 86%Start: March 2017
Net Costs: $70,000.00 approx.
Multi-Year Project: No
Procurement Method :LVP
Description
Hilber road was not designed for two way tractor
trailer use .
Rationale
The road will have to be widened to accommodate
new use. (1000 x 15 ) wide (2 to 7 ) deep
Cell 4 A-
construction
$3,130,000
External Funding:Valley 86%Start: March 2017
Net Costs: $3,130,000
Multi-Year Project: (Y or N) No
Procurement Method (HVP or LVP) HVP
Description
New cell to accommodate waste and prepare for
accommodating the Sustane solution
Rationale
The new sell will hold 90,000 MT this will cover us
until Sustane is operating .
1Ton truck
$50,000
External Funding: Valley 86%Start: 2017
Net Costs: $50,000.00
Multi-Year Project: (Y or N) No
Procurement Method (HVP or LVP) HVP
Description
Replace 2007 1 ton truck.
Rationale
The 1 ton is used to sand roads and plow main
road once opened by loader. It is fundamental to
the operation. The age and constant use has
required an increase in repairs.
Chlorine
contact
chamber
$25,000
External Funding:No Start: May 2017
Net Costs: $25,000.00
Multi-Year Project: No
Procurement Method :HVP
Description
Reinstate contact chamber servicing second sewer
lagoon
Rationale
This will be used only when the lagoon is at risk
from prolonged storm water
Community
Development
2017-18 Capital Projects
Business Park
Development
& Land
Acquisition
$450,000
External Funding:No Start: May 2017
Net Costs: $450,000
Multi-Year Project: Y
Procurement Method :Alternate Procurement
Description
Purchase of land for potential future development
of a business/industrial park
Rationale
This will allow council to secure the lands and
begin planning for a phased in development of a
future business industrial park.
Parking Study
$35,000
External Funding:No Start: May 2017
Net Costs: 35,000
Multi-Year Project: N
Procurement Method :LVP
Description
Hiring of a consultant to study parking demand in the
Village of Chester, with a focus on the village core.
Rationale
This will identify if there is a real or perceived parking
issue, if the issue is seasonal or year-round, and it will
identify potential solutions. This is not a
comprehensive traffic study that would look at larger
circulation issues or the need to reconfigure/reclassify
streets.
Permit
Tracking
Software
$60,000
External Funding:Y Start: May 2017
Net Costs: $60,000
Multi-Year Project: N
Procurement Method HVP
Description
Potential replacement of permit tracking software
with a solution that would have both allow
mapping, route scheduling and inspection
scheduling.
Rationale
This software would allow for increased
efficiencies and better integration with existing
platforms, including laserfiche.
Floodplain
Modelling
$100,000
External Funding:Gas Tax Start: May 2017
Net Costs: 0
Multi-Year Project: No
Procurement Method: HVP
Description
This is a carry over of the LIDAR mapping and
floodplain mapping project in 2016/17. The Lidar
was collected but the data will not be ready to use
for the second phase of the project until the end of
FY 16/17.
Rationale
This will provide data for both coastal areas (sea
level rise, storm surge) and inland flooding
Rural
Internet
Backbone –
Broadband
Design
$50,000
External Funding: Gas Tax Start: May 2017
Net Costs: $0
Multi-Year Project: Yes
Procurement Method :HVP
Description
A multi-year project to design a backbone for rural
internet across MODC. This phase is Design
Rationale
This will be the first step providing high-speed internet
to residents where internet service is unreliable and
inadequate. The backbone will be required to be an
open system, that would allow independent or
competing companies to access the network.
Information
Services
2017-18 Capital Projects
GPS UNIT
$20,000
External Funding: No Start: June 2017
Net Costs: $20,000
Multi-Year Project: No
Procurement Method LVP
Description
GPS equipment allows us to collect the GPS
locations of all our asset areas. Asset Collection is
critical to the foundation of any Asset Mgt System.
Rationale
Our current unit is 10 years old.
Engineering
& Public
Works
2017-18 Capital Projects
Collection
System –
Cleaning &
Videoing -
$20,400
External Funding: $10,200 (PCAP) Start: Sept 2017
Net Costs: $10,200 (Area Rate)
Multi-Year Project: Y –Year 5 of 5
Procurement Method: LVP –Service Tender
Description
Part of Infiltration and Inflow reduction program. The
collection systems are cleaned and videoed through
CCTV. Enables identification of deficiencies and the
development of “master plan” for repairs. Sections are
to be done in both Chester and Western Shore.
Rationale
Improves wastewater collection & treatment; reduces
costs associated with back-ups and overflows; enables
master plan to be developed
Manhole
Repairs &
Infiltration
Reduction
Program -
$40,800
External Funding: $ 20,400 (PCAP) Start: May 2017
Net Costs: $ 20,400 (Area Rate)
Multi-Year Project: Y –Year 5 of 5
Procurement Method: HVP -Sewer Repair Contract
Description
Inspection, repair and raised to surface: Western Shore
(20), Chester (20) and Mill Cove (5) . Contracting out
Heavy Equipment and Traffic Control; In-house Labour.
Rationale
Addresses Inflow and Infiltration; Improves waste
water treatment efficiency; reduces overflows; reduces
cost of transmittance and wastewater; best practice
Pump
Replacement
$15,300
External Funding:$0 Start: As required
Net Costs: $15,300 (Area Rate)
Multi-Year Project: Y –Ongoing
Procurement Method: Alternative Procurement
Description
Allowance to replace a limited amount of pumps
associated with collection and treatment.
Rationale
Enables purchase of pumps in the event of
breakdown (where cost of repair is too high)
Chester
Wastewater
System
Assessment
$15,000
External Funding:$0 Start: May 2017
Net Costs: $15,000 (Sewer Reserve)
Multi-Year Project: N
Procurement Method: HVP –Engineering Contract
Description
Operational assessment. Reviewing effluent, treatment
technology, capacity, regulatory compliance, receiving
water quality, capital improvements, inflow and
infiltration assessment.
Rationale
NSE Approval to Operate Requirement –Dec 4, 2017
Adherence to AC Guidelines Manual –Jan 1, 2020
Chester Basin
Wastewater
System
Assessment
$7,500
External Funding:$0 Start: May 2017
Net Costs: $7,500 (Sewer Reserve)
Multi-Year Project: N
Procurement Method: HVP –Engineering Contract
Description
Operational assessment. Reviewing effluent, treatment
technology, capacity, regulatory compliance, receiving
water quality, capital improvements, inflow and
infiltration assessment.
Rationale
NSE Approval to Operate Requirement –Dec 4, 2017
Adherence to AC Guidelines Manual –Jan 1, 2020
Chester PS 4
Refurbishing
$15,300
External Funding:Start: May 2017
Net Costs: $15,300 (Sewer Reserve)
Multi-Year Project: N
Procurement Method: LVP –Request for Quotation
Description
Replumbing the lift station, replacing worn out
discharge piping, valving, rails and installing
pumps.
Rationale
Improve operation and reduce the frequency of
breakdowns and callouts.
Mill Cove
Wastewater
Treatment
Plant
Replacement
$1,400,000
External Funding: $1.05M (CWWF) Start: May 2017
Net Costs: $350,000 ($150K –Reserve; $200K-Borrow)
Multi-Year Project: N
Procurement Method: HVP –Construction Tender
Description
New WWTP , incorporating modern filtration
treatment system, using existing outfall, with capacity
to treat existing customers, plus properties fronting
system
Rationale
Existing system is 50 years old, in poor condition and at
risk of failure; Comprehensive review in 2013
recommended replacement
Mill Cove
Wastewater
System
Assessment
$10,000
External Funding:$0 Start: May 2017
Net Costs: $10,000 (Area Rate)
Multi-Year Project: N
Procurement Method: HVP –Engineering Contract
Description
Operational assessment. Reviewing effluent, treatment
technology, capacity, regulatory compliance, receiving
water quality, capital improvements, inflow and
infiltration assessment.
Rationale
NSE Approval to Operate Requirement –May 1, 2017
Adherence to AC Guidelines Manual –Jan 1, 2020
Otter Point
Wastewater
Treatment
Plant –Bldg.
Replacement
& Repairs
$12,500
External Funding: $0 Start: May 2017
Net Costs: $12,500 (Reserve)
Multi-Year Project: N
Procurement Method: Purchase materials only
Labour in-house
Description
Constructing new buildings over the filtration tank.
Increase size (height) and access.
Rationale
The buildings are over 40 years old and are falling
apart. Need to improve access for maintenance.
Otter Point
Wastewater
System
Assessment
$7,500
External Funding:$0 Start: May 2017
Net Costs: $7,500 (Reserve)
Multi-Year Project: N
Procurement Method: HVP –Engineering Contract
Description
Operational assessment. Reviewing effluent, treatment
technology, capacity, regulatory compliance, receiving
water quality, capital improvements, inflow and
infiltration assessment.
Rationale
NSE Approval to Operate Requirement –July 4, 2017
Adherence to AC Guidelines Manual –Jan 1, 2020
Village of
Chester
Central
Water
System
Design
$500, 000
External Funding:Start: May 2017
Net Costs: $500,000
Multi-Year Project: Y
Procurement Method: HVP –Engineering Contract
Description
Designing the recommended solution from the
VOC Needs Assessment & Options Analysis Study
Rationale
Municipal Council/Village of Chester initiative to
design a cost effective solution to the assessed
water needs in the Village of Chester.
Chester
Wastewater
Plant –
Property
Improvement
$10,200
External Funding:Start: May 2017
Net Costs: $10,200 (Reserve)
Multi-Year Project: N
Procurement Method: LVP
Description
Installation of aluminum railings around open below
ground concrete structures make repairs to steel
gangways/bridges, paint buildings and concrete
structures
Rationale
Improve site safety, responds to safety inspection
deficiencies and improves condition of property and
structures
Western
Shore
Wastewater
System
Assessment
$15,000
External Funding:$0 Start: May 2017
Net Costs: $15,000 (Reserve)
Multi-Year Project: N
Procurement Method: HVP –Engineering Contract
Description
Operational assessment. Reviewing effluent,
treatment technology, capacity, regulatory
compliance, receiving water quality, capital
improvements, inflow and infiltration assessment.
Rationale
NSE Approval to Operate Requirement –TBA
Adherence to AC Guidelines Manual –Jan 1, 2020
Western
Shore
Wastewater
Plant
Upgrades
$1,555,000
External Funding: $1.16M (CWWF) Start: May 2017
Net Costs: $388,750 (Borrow)
Multi-Year Project: Y
Procurement Method: HVP –Construction Tender
Description
Focus is on installing surge (high-flows) protection and
replacing the disinfection system. Also, if funding
allows, the scopes includes the construction of a new
operations building, process controls, refurbishment of
clarifier, back-up power, and sludge wasting
improvements.
Rationale
The plant is over 40 years old, requires upgrades to
meet NSE Approval to Operate and modifications to
improve operations.
Municipal &
Annex
Building
Improvement
& Repairs
$100,000
External Funding:$0 Start: Ongoing
Net Costs: $100,000
Multi-Year Project: Y
Procurement Method: LVP
Description
Misc. interior /exterior repairs; committee room
update; Annex Bldg. Renovation –Upper Level
(meeting room; reception)
Rationale
Option to address need for additional office/storage
space; Ability to address needed maintenance / repair
Mill Cove Fire
Protection
System –
Distribution
Repairs
$35,000
External Funding:Start: May 2017
Net Costs: $35,000
Multi-Year Project: Y
Procurement Method: LVP
Description
Replacing portions of the distribution branches
and associated Fire Hydrants
Rationale
Recommendation from the Mill Cove Fire
Suppression System Evaluation. Fire Protection is
currently compromised.
Mill Cove Fire
Protection
Sys. Design
(Decommissi
on Review)
$20,000
External Funding:Start: May 2017
Net Costs: $20,000
Multi-Year Project: Y
Procurement Method: HVP –Engineering Contract
Description
Either undertake the design of (1) of the three options
for the rehabilitation of the Fire Protection system or if
determined feasible by Staff, undertake the design of
system decommissioning.
Rationale
Recommendation from the Mill Cove Fire Suppression
System Evaluation. Fire Protection is currently
compromised.
Direction
Required
Outstanding
-Fire Truck
-Fire Services for “Outside Areas”…should we start
a reserve; plan capital etc.?
-GRWS Property-Assumes no plans at this point.
-NSDOTIR-Road Upgrades-Reserves?
-Zoe Valle Library $44,160 (exterior cladding;
window trim; storm windows)
What would you like to see changed?
-Added?
-Removed?
-Revised?
Capital Budget Review - 2017/18
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/17 (Estimated)47,500 4,356,400 1,126,800 642,078 42,500 168,500 4,963,000 29,100 353,055
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$15,000 2 15,000
2 Trails - Bridge Evaluation 25,000 1 25,000
3 Trails - Swing Gates Project 7,800 1 7,800
4 Land Acquisition - Parkland 170,000 100,000 70,000
5 East River Trail 25,000 1 3,000 22,000
6 Specticle Lake Cottage Demolition 15,000 1 15,000
7 Gold River Park Land/Playground 10,000 1 10,000
$267,800
CAO/Administration
1 PACE By-law (Wells)$200,000 1 200,000
$200,000
Solid Waste
Landfill Only Projects (Valley)
1 Snowplowed skid steer $9,800 1 9,800
2 Office roof shingle-metal $12,000 1 12,000
3 Main Leachate Pump $20,000 1 20,000
4 Convert to roll off truck * 3 containers $60,000 3 60,000
5 Second tower site $200,000 1 200,000
6 Road Upgrade $70,000 1 70,000
7 Cell 4A Design and Construction 3,130,000 1 3,130,000
8 Truck Replacement - 1 tonne Plow truck with dump box-Landfill65,000 1 65,000
Solid Waste Projects (Chester only)
1 Chlorine Contact Chamber $25,000 1 25,000
$3,591,800
Community Development
1 ED-Industrial Park Development/Acquisition 450,000 2 450,000
2 Parking Study 35,000 2 35,000
3 Permit Tracking Software 60,000 60,000
4 Flood Plain Modelling 100,000 1 100,000
5 Backbone - Broadband Design 50,000 1 50,000
$695,000
Information Services
1 GPS Units $20,000 20,000
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Blue Area $20,400 2 10,200 PCAP 10,200
2 Manhole Repairs & Infiltration Reduction 40,800 2 20,400 PCAP 20,400
3 Pump Replacements - Allowance 15,300 2 15,300
$76,500
Chester Sewer:
1 System Assessment - Chester $15,000 1 15,000
2 System Assessment - Chester Basin $7,500 1 7,500
3 Pump Station Refurbished - Chester PS 4 $15,300 1 15,300
$37,800
Mill Cove Sewer:
1 Wastewater Plant Improvements - New Plant $1,400,000 1 150,000 1,050,000 BCF Infrastructure 200,000
2 System Assessment - Mill Cove $10,000 1 10,000
Otter Point Sewer:
1 WWTP Bldg Replacement & Repairs $12,500 2 12,500
2 System Assessment $7,500 1 7,500
$20,000
Village of Chester:
1 VOC Water System - Design $500,000 2 500,000
2 Property Improvements - WWTPs 10,200 10,200
Western Shore Sewer:
1 System Assessment - WS 15000 15,000
2 WWTP Upgrades - UV & Building Upgrades $1,555,000 1 1,166,250 388,750
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 100,000 1 100,000
2 Fire Protection System Distribution & Repairs -Mill Cove 35,000 35,000
3 Fire Protection System Design - Decommissioning Review-Mill Cove20,000 1 20,000
$155,000
Public Works Total $3,779,500
Total Projects & Funding Contributions $8,554,100 0 588,000 197,800 450,000 0 80,000 0 0 233,000 2,268,850 0 86,800 55,900 4,593,750
Reserve Balance 47,500 3,768,400 929,000 192,078 42,500 88,500 4,963,000 29,100 120,055
Operation Expenditures 0 50,000 0 0 0 0 0 0 0
Contributions 2016/17 350,000 570,000 958,578 0 10,000 335,000 34,500 141,000
Interest Earned 500 50,000 20,000 12,000 500 500 108,000 600 2,400
Balance March 31, 2018 48,000 4,118,400 1,519,000 1,162,656 43,000 99,000 5,406,000 64,200 263,455
Capital Budget Review - 2018/19
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/18 (Estimated)$48,000 $4,118,400 $1,519,000 $1,162,656 $43,000 $99,000 $5,406,000 $64,200 $263,455
RECREATION & PARKS
1 Trails - Bridge Evaluation 20,000 1 20,000
2 Trails - Swing Gates Project 7,500 1 7,500
3 Deep Cove Parking Lot/Fishing 25,000 1 25,000
$52,500
CAO/Administration
1 Wind Farm 550,000 1 550,000
2 Internet-Backbone 750,000 1 750,000
3 PACE By-law (Wells)$200,000 1 $200,000
$1,500,000
Solid Waste
Landfill Only Projects (Valley)
1 Dredging (not Valley) $60,000 1 $60,000
2 Road Improvements 40,000 1 $40,000
3 Scale 0 1 $0
4 Excavator 225,000 1 $225,000
$325,000
Community Development
1 ED-Industrial Park Development/Acquisition 200,000 2 200,000
2 Highway 3 Streetscape Implementation 80,000 3 80,000
$280,000
Information Services
1 Ortho Photography 100,000 1 100,000
$100,000
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Green $15,700 2 7,850 PCAP 7,850
2 Manhole Repairs & Infiltration Reduction 41,700 2 20,850 PCAP 20,850
3 Pump Replacements - Allowance 15,700 2 15,700
$73,100
Chester Sewer:
1 WWTP Improvements - UV/Sludge Chester $30,000 1 30,000
2 WWT Improvements-Flow Monitoring/UV -Chester Basin $12,500 1 $12,500
$42,500
Otter Point Sewer:
1 WWTP - Plant Expansion/Outfall/UV - Otter Point $42,500 2 42,500
$42,500
Village of Chester:
1 VOC Water System-Design $500,000 2 500,000
2 Property Improvements - WWTPs 10,500 10,500
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 80,000 1 80,000
2 Truck Replacement - 1/2 tonne (Bldg Inspn)40,600 1 40,600
3 Wild Rose Park Drainage 30,000 2 30,000
4 Fire Protection System - Distribution System Repairs 35,000 2 35,000
5 Fire Protection System - Option Selected-Phase 1 40,000 1 40,000
$225,600
Roads & Sidewalks
1 Sidewalk Drainage - Duke Street $45,000 2 45,000
2 Chester Basin - Wharf Repairs 65,125 2 17,000 48,125
$110,125
Public Works Total $1,004,325
Total Projects & Funding Contributions $3,261,825 $0 $1,072,000 $207,500 $750,000 $0 $0 $0 $0 $83,000 $28,700 $0 $163,725 $56,900 $900,000
Reserve Balance $48,000 $3,046,400 $1,311,500 $412,656 $43,000 $99,000 $5,406,000 $64,200 $180,455
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2019 $48,500 $3,396,400 $1,901,500 $1,383,234 $43,500 $109,500 $5,849,000 $99,300 $323,855
Capital Budget Review - 2019/20
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/19 (Estimated)$48,500 $3,396,400 $1,901,500 $1,383,234 $43,500 $109,500 $5,849,000 $99,300 $323,855
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$20,000 3 $20,000
2 ATV Replacement 17,500 1 17,500
$37,500
CAO/Administration
2 PACE By-law (Wells)$200,000 1 200,000
$200,000
Solid Waste
Landfill Only Projects (Valley)
1 Road Improvements 40,000 1 40,000
2 3/4 Tonne Truck 25,000 1 25,000
$65,000
Community Development
1 ED-Industrial Park Development/Acquisition 1,000,000 2 1,000,000
2 Highway 3 Streetscape Implementation 150,000 3 150,000
$1,150,000
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Pink $16,000 2 8,000 PCAP 8,000
2 Manhole Repairs & Infiltration Reduction 50,400 2 25,200 PCAP 25,200
3 Pump Replacements 16,000 2 16,000
$82,400
Chester Sewer:
1 WWTP Improvements - UV/Sludge Chester $250,000 1 250,000
2
WWT Improvements-Flow Monitoring/UV -Chester
Basin $100,000 1 100,000
$350,000
Otter Point Sewer:
1
WWTP & Collection Plant Expansion/Outfall /UV
Otter point $150,000 1 150,000
$150,000
Village of Chester:
1 VOC Water System (MODC's share) $2,750,000 2
Western Shore Sewer:
1 Wastewater Plant Improvements - Western Shore $30,000 1 30,000
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 25,500 1 25,500
2 Property Improvements - WWTPs 10,700 2 10,700
3 Truck Replacement - 3/4 tonne (Prop Mtce)45,700 2 45,700
4 Fire Protection System - Option Selected-Phase 1 300,000 1 300,000
$381,900
Public Works Total $3,744,300
Total Projects & Funding Contributions $5,196,800 $0 $225,500 $450,000 $0 $17,500 $0 $0 $0 $250,000 $33,200 $0 $45,700 $59,900 $1,365,000
Reserve Balance $48,500 $3,170,900 $1,451,500 $1,383,234 $26,000 $109,500 $5,849,000 $99,300 $73,855
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2020 $49,000 $3,520,900 $2,041,500 $2,353,812 $26,500 $120,000 $6,292,000 $134,400 $217,255
Capital Budget Review - 2020/21
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/20 (Estimated)$49,000 $3,520,900 $2,041,500 $2,353,812 $26,500 $120,000 $6,292,000 $134,400 $217,255
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$15,000 3 $15,000
2 Trails - Bridge Evaluation 20,000 1 20,000
$35,000
CAO/Administration
1 KM Turbine 50,000 50,000
2 PACE By-law (Wells)$150,000 1 150000
$200,000
Solid Waste
Landfill Only Projects (Valley)
1 Miscellaneous $50,000 1 $50,000
2 Road Improvements (Valley @ 20%)40,000 1 40,000
$90,000
Community Development
1 ED-Industrial Park Development/Acquisition 500,000 2 500,000
2 Highway 3 Streetscape Implementation 150,000 3 150,000
$650,000
Information Services
1 VMWARE Infrastructure 60000 60,000
2 Hardware Replacement 86600 1 86,600
$146,600
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Orange $16,300 2 8,150 PCAP 8,150
2 Manhole Repairs & Infiltration Reduction 54,500 2 27,250 PCAP 27,250
3 Pump Replacements - Allowance 16,300 2 16,300
$87,100
Chester Sewer:
1 WWTP Improvements - Clarifier #2 Rebuild - Chester $100,000 1 100,000
$100,000
Village of Chester:
1 VOC Water System (MODC share's)$2,750,000 2
Western Shore Sewer:
1 WWTP Upgrades - UV & Building Upgrades $300,000 1 300,000
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 11,300 1 11,300
2 Property Improvements - WWTPs 10,900 2 10,900
3 Truck Replacement - 1/2 tonne (Curbside Insp)42,300 2 42,300
$64,500
Public Works Total $3,301,600
Total Projects & Funding Contributions $4,423,200 $0 $161,300 $285,000 $550,000 $0 $0 $0 $146,600 $0 $35,400 $0 $42,300 $62,600 $390,000
Reserve Balance $49,000 $3,359,600 $1,756,500 $1,803,812 $26,500 $120,000 $6,292,000 -$12,200 $217,255
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2021 $49,500 $3,709,600 $2,346,500 $2,774,390 $27,000 $130,500 $6,735,000 $22,900 $360,655
Capital Budget Review - 2021/22
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/21 (Estimated)$49,500 $3,709,600 $2,346,500 $2,774,390 $27,000 $130,500 $6,735,000 $22,900 $360,655
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$15,000 3 $15,000
2 Trails - Bridge Evaluation 20,000 1 20,000
3 Hawboolt Trail 60,000 2 60,000
$95,000
CAO/Administration
1 Chester Wind Project - Repairs & Upgrades
2 PACE By-law (Wells)$100,000 1 100000
$100,000
Solid Waste
Landfill Only Projects (Valley)
1 Miscellaneous $50,000 1 $50,000
Solid Waste Projects (Chester only)
1 Miscellaneous $50,000 1 50,000
Community Development
1 GPS Units 20,000 1 20,000
2 Highway 3 Streetscape Implementation 150,000 3 150,000
$170,000
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Blue $16,600 2 8,300 PCAP 8,300
2 Manhole Repairs & Infiltration Reduction 22,100 2 11,050 PCAP 11,050
3 Pump Replacements - Allowance 16,600 2 16,600
$55,300
Otter Point Sewer:
1 Pumping Station Improvements 44,200 2 44,200
$44,200
Village of Chester:
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 11,600 2 11,600
2 Property Improvements -Headworks/Ditch Lining 30,000 2 30,000
3 Property Improvements - WWTPs 11,100 2 11,100
4 Truck Replacement - 3/4 tonne (Prop Mtce)47,500 2 47,500
5 Fire Protection System - Option Selected-Phase 2 20,000 1 20,000
2
$120,200
Public Works Total $219,700
Total Projects & Funding Contributions $684,700 $0 $131,600 $245,000 $0 $0 $0 $0 $0 $0 $19,350 $0 $47,500 $121,250 $120,000
Reserve Balance $49,500 $3,578,000 $2,101,500 $2,774,390 $27,000 $130,500 $6,735,000 $22,900 $360,655
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2022 $50,000 $3,928,000 $2,691,500 $3,744,968 $27,500 $141,000 $7,178,000 $58,000 $504,055
Capital Budget Review - 2022/23
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/22 (Estimated)$50,000 $3,928,000 $2,691,500 $3,744,968 $27,500 $141,000 $7,178,000 $58,000 $504,055
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$15,000 3 $15,000
2 Trails - Bridge Evaluation 20,000 1 $20,000
$35,000
CAO/Administration
1 KM Turbine 25,000 25,000
2 PACE By-law (Wells)$100,000 1 100000
$125,000
Solid Waste
Landfill Only Projects (Valley)
1 Miscellaneous $50,000 1 $50,000
2 Loader 200,000 1 200,000
$250,000
Community Development
1 Highway 3 Streetscape Implementation 150,000 3 150,000
$150,000
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Yellow $16,900 2 8,450 PCAP 8,450
2 Manhole Repairs & Infiltration Reduction 22,600 2 11,300 PCAP 11,300
3 Pump Replacements - Allowance 16,900 2 16,900
$56,400
Otter Point Sewer:
1 WWTP Improvements - Second Leg-Otter Point $250,000 2 250,000
$250,000
Western Shore Sewer:
1 WWTP Upgrades - Sludge Wasting 30000 2 30,000
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 35,300 1 35,300
2 Property Improvements -Headworks/Ditch Lining 300,000 1 300,000
3 Property Improvements - WWTPs 11,300 2 11,300
4 Truck Replacement - 3/4 tonne Sewer 48,500 2 48,500
5 Fire Protection System - Option Selected-Phase 2 150,000 1 150,000
2
$545,100
Public Works Total $881,500
Total Projects & Funding Contributions $1,441,500 $0 $135,300 $185,000 $25,000 $0 $0 $0 $0 $0 $19,750 $0 $48,500 $77,950 $950,000
Reserve Balance $50,000 $3,792,700 $2,506,500 $3,719,968 $27,500 $141,000 $7,178,000 $58,000 $504,055
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2023 $50,500 $4,142,700 $3,096,500 $4,690,546 $28,000 $151,500 $7,621,000 $93,100 $647,455
Capital Budget Review - 2023/24
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/23 (Estimated)$50,500 $4,142,700 $3,096,500 $4,690,546 $28,000 $151,500 $7,621,000 $93,100 $647,455
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$15,000 3 $15,000
2 Trails - Bridge Evaluation 20,000 1 $20,000
3 Playground Improvement - Croft Road 20,000 1 20,000
$55,000
CAO/Administration
1 PACE By-law (Wells)$100,000 1 100000
$100,000
Solid Waste
Landfill Only Projects (Valley)
1 Miscellaneous $50,000 1 $50,000
Community Development
1 ED-Industrial Park Development/Acquisition 1,000,000 2 600,000 400,000
2 Highway 3 Streetscape Implementation 150,000 3 150,000
$1,150,000
Information Services
1 Ortho Photography 100000 100,000
$100,000
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Green $17,300 2 8,650 PCAP 8,650
2 Manhole Repairs & Infiltration Reduction 23,000 2 11,500 PCAP 11,500
3 Pump Replacements - Allowance 17,300 2 17,300
$57,600
Western Shore Sewer:
1 WWTP Upgrades - Sludge Wasting- (Geotubes)250,000 2 250,000
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 19,500 1 19,500
2 Property Improvements - WWTPs 11,500 2 11,500
3 Truck Replacement - 3/4 tonne Sewer 49,400 2 49,400
$80,400
Public Works Total $388,000
Total Projects & Funding Contributions $1,843,000 $0 $119,500 $285,000 $600,000 $0 $20,000 $0 $0 $0 $20,150 $0 $49,400 $48,950 $700,000
Reserve Balance $50,500 $4,023,200 $2,811,500 $4,090,546 $28,000 $131,500 $7,621,000 $93,100 $647,455
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2024 $51,000 $4,373,200 $3,401,500 $5,061,124 $28,500 $142,000 $8,064,000 $128,200 $790,855
Capital Budget Review - 2024/25
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/24 (Estimated)$51,000 $4,373,200 $3,401,500 $5,061,124 $28,500 $142,000 $8,064,000 $128,200 $790,855
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$15,000 3 $15,000
2 Trails - Bridge Evaluation 20,000 1 $20,000
$35,000
CAO/Administration
1 Chester Wind Project - Repairs & Upgrades
2 KM Turbine 50,000 50,000
3 PACE By-law (Wells)$100,000 1 100000
$150,000
Solid Waste
Landfill Only Projects (Valley)
1 Miscellaneous $50,000 1 $50,000
Solid Waste Projects (Chester only)
1 1 Ton Truck 50,000 $50,000$100,000
Community Development
1 ED-Industrial Park Development/Acquisition 500,000 2 300,000 200,000
2 Highway 3 Streetscape Implementation 150,000 3 150,000
$650,000
Information Services
1 VMWARE Infrastructure 60000 60,000
2 Hardware Replacement 86600 1 86,600
$146,600
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Pink $17,600 2 8,800 PCAP 8,800
2 Manhole Repairs & Infiltration Reduction 23,500 2 11,750 PCAP 11,750
3 Pump Replacements - Allowance 17,600 2 17,600
$58,700
Chester Sewer:1 WWTP Improvements - Automation & Areration - Chester $35,000 2 35,000
$35,000
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 28,200 1 28,200
2 Property Improvements - WWTPs 11,800 2 11,800
3 Truck Replacement - 1 tonne plow truck with dump box 76,200 1 76,200
$116,200
Public Works Total $209,900
Total Projects & Funding Contributions $1,291,500 $0 $128,200 $185,000 $350,000 $0 $0 $0 $146,600 $0 $20,550 $0 $76,200 $84,950 $300,000
Reserve Balance $51,000 $4,245,000 $3,216,500 $4,711,124 $28,500 $142,000 $8,064,000 -$18,400 $790,855
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2025 $51,500 $4,595,000 $3,806,500 $5,681,702 $29,000 $152,500 $8,507,000 $16,700 $934,255
Capital Budget Review - 2025/26
January 16, 2017
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Balance March 31/25 (Estimated)$51,500 $4,595,000 $3,806,500 $5,681,702 $29,000 $152,500 $8,507,000 $16,700 $934,255
RECREATION & PARKS
1 Trails - Surface Upgrades (AT 6.20)$15,000 3 $15,000
2 Trails - Bridge Evaluation 20,000 1 $20,000
$35,000
CAO/Administration
1 PACE By-law (Wells)$100,000 1 100000
$100,000
Solid Waste
Landfill Only Projects (Valley)
1 Miscellaneous $50,000 1 $50,000
Community Development
1 Highway 3 Streetscape Implementation 150,000 3 150,000
$150,000
Project Capital Operating Gas Tax Wind Revenue Recreation Parkland Landfill Close.Equipment Sewer Grants/Other Fund from Fund from Fund from
Project Cost Category Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Reserve Funds Operations Area Rate Borrowing
Public Works
Universal Sewer Projects:
1 Collection Systems - Cleaning & Videoing - Orange $18,000 2 9,000 PCAP 9,000
2 Manhole Repairs & Infiltration Reduction 24,000 2 12,000 PCAP 12,000
3 Pump Replacements - Allowance 18,000 2 18,000
$60,000
Chester Sewer:
1 WWTP Improvements - Automation & Areration - Chester $350,000 1 350,000
$350,000
Western Shore Sewer:
1 WWTP Upgrades - Clarifier 35000 2 35,000
Municipal Property:
1 Municipal Building Improvements & Repairs-Annex 12,500 1 12,500
2 Property Improvements - WWTPs 12,000 2 12,000
3 Truck Replacement - 1/2 tonne (Bldg Insp)46,700 1 46,700
$71,200
Public Works Total $516,200
Total Projects & Funding Contributions $851,200 $0 $112,500 $185,000 $0 $0 $0 $0 $0 $0 $21,000 $0 $46,700 $86,000 $400,000
Reserve Balance $51,500 $4,482,500 $3,621,500 $5,681,702 $29,000 $152,500 $8,507,000 $16,700 $934,255
Operation Expenditures $0 $50,000 $0 $0 $0 $0 $0 $0 $0
Contributions 2016/17 $0 $350,000 $570,000 $958,578 $0 $10,000 $335,000 $34,500 $141,000
Interest Earned $500 $50,000 $20,000 $12,000 $500 $500 $108,000 $600 $2,400
Balance March 31, 2026 $52,000 $4,832,500 $4,211,500 $6,652,280 $29,500 $163,000 $8,950,000 $51,800 $1,077,655